OEG Renewables offshore wind turbine clear blue sky

Case study

Temporary power provision for Hornsea Two offshore wind farm

Overview

OEG's topside division signed a major contract with Ørsted in 2021 for the provision of the full temporary power solution, service technicians and both crew transfer and walk to work vessels, during the construction phase of the Hornsea Two offshore wind farm.

Located 89 km off the UK coast and adjacent to the Hornsea One offshore wind farm, the project consists of 165 SGRE 8.0-167 type turbines, giving a total capacity of 1.4 GW; on completion it has become the largest offshore wind farm in the world.

All 165 wind turbines became fully operational in August 2022 and the project will help power over 1.4 million UK homes.

Client

Ørsted

Location

Hornsea Two, U.K

Hornsea two temporary power
Manor venture on hornsea two
Horizon star hornsea two
×

Gallery view

Challenges

Supplying temporary power solutions, vessels and personnel to the largest offshore wind farm in the world.

Workscope

To provide temporary power, personnel and vessels to support the construction phase of the project.

Contract duration was from May 2021 until September 2022, with 485 days onsite overall and zero harm incidents.

Solution

OEG's topside division installed 165 116QS temporary power generators offshore, supported by CTVs and SOVs. OEG supplied owned and chartered CTVs to the project, with two operating at one time; both the Manor Endurance and Manor Venture were on site. OEG chartered three SOVs during the duration of the project, including the Normand Fortress, Acta Orion and Horizon Star.

Approximately 90 personnel worked on the project throughout the work scope; at peak, 58 personnel were on shift including both on and offshore roles. OEG's dedicated project office in Hull supported the operations on Hornsea Two and provided a storage space for the generator sets.

All generators sets were demobilised by September 2022.